1. identify one type of project management tool that could be used to keep track of the project tasks and explain why it is suitable for this task. [3]
A project management tool such as a production schedule (1 mark) would be suitable to use for creating the road safety computer game as it outlines (1 mark) tasks which need to be done in a certain time in order for the product to be ready for the client, this is also suitable because it create a chronological order for the tasks to be completing and organises them due to the timescales.
To create a production schedule you could use a software like excel as you can easily insert timescales and tasks into the table which need to be completed. (1 mark)
3 marks very good
Try and include a production schedule i.e. it would be given to all staff/personnel etc.
Peer assessor Darcy